Lyell Collection

Quarterly Journal of Engineering Geology and Hydrogeology

Lyell Centre  |   Lyell Collection  |   Subscriptions   |   Geological Society  |   Email alerts  |   Online bookshop  |   Help


Keywords:
Author:
Advanced search>>
This Article
Right arrow Full Text (PDF)
Right arrow References
Right arrow Alert me when this article is cited
Right arrow Alert me if a correction is posted
Services
Right arrow Email this article to a friend
Right arrow Similar articles in this journal
Right arrow Alert me to new issues of the journal
Right arrow Download to citation manager
Right arrow Request Permissions
Citing Articles
Right arrow Citing Articles via Google Scholar
Google Scholar
Right arrow Search for Related Content
Quarterly Journal of Engineering Geology and Hydrogeology; 1978; v. 11; issue.3; p. 265;
DOI: 10.1144/GSL.QJEG.1978.011.03.07
© 1978 Geological Society of London

Discussion

Reply by Dr J. M. Edmond and Mr J. D. Graham

We would like to thank Dr Barton for his comments, which dealt principally with the material forming the Appendix to the paper. The basis for Dr Barton's hindsight ‘prediction’ for systematic support of 2.5 m long bolts at 1 m spacing plus 50 mm of reinforced shotcrete (with its similarity to the engineers' enquiry specification shown on pp. 291 and 292, and figs. 9 and 10) is interesting although inherently probably somewhat subjective.

It must be emphasised that the NGI system was not available to us at the time of the tunnel investigation and was only briefly appended to the case study in order to try to compare it, albeit rather superficially, with the Bieniawski (1973) system. We tried however to be as objective as possible in applying it on the basis of the site investigation results only.

The basic approach to design was that the rock, together with its primary support system, provided the main strength of the tunnel. Such primary system was a permanent part of the works. For a hydraulic tunnel such as this one a smooth circular concrete surface was required, Over the life of the structure the provision of this concrete lining, together with grouting measures, consolidates and completes the tunnel strength, durability and serviceability. From the results of the site investigation the recommended primary support for those lengths of the tunnel which were not highly weathered was based largely upon one of Bieniawski's

...

This 250-word extract was created in the absence of an abstract.